The implementation of the national project “Safe Quality Roads” (BKD) in our city continues.
Right now, according to this project, from Stusev Street to Veresova Street, within the boundaries of the red lines of the Kolmovskaya embankment, a section of the road is being built.
“Preparatory works by the contractor have been completed – the vegetation has been cut down, trees have been cut down. Reinforced concrete elements for the installation of storm sewers were delivered to the facility, “says Artyom Korolev, head of the production and technical department of the capital construction department. “The construction of the road is on schedule.
In addition to the roadway, the project envisages the construction of two-sided bicycle lanes, one side combined with the sidewalk, as well as rainwater drainage, external electric lighting. Road signs and markings will also appear here.
Recall that a contract worth 43.6 million rubles for the construction of this section of the road with a length of 522 meters was concluded with Stroy-M OOO. According to it, the contractor’s work should be completed on December 1 of this year.
The day before, the mayor of Veliky Novgorod Alexander Rozbaum, after visiting the facility, wrote on his VKontakte page: “… I checked what was done during the week and what needs to be done in the coming days. There isn’t much time left until the end of the year, so every day counts in the construction cycle. UKS Veliky Novgorod daily monitors the progress of the work. We make a concerted effort to complete all construction projects on time. We work together!